Construction progress
Ми готуємо для вас пости, скоро тут буде не порожньо

March 2026
13.03.2026
Section 1.2-1.3
- Construction of the pit -80%
Section 1.1
- Installation of waterproofing -80%
- Construction of the frame of the building —90%
- Installation of masonry -20%
- Installation of ventilation units -20%
Section 2.1
- Construction of the pit -100%
Parking 3
Foundation installation -90%

Februar 2026
13.02.2026
Installation of vertical waterproofing of the plinth is completed
Arrangement of the floor slab of the 5th floor of section 1
Construction of the pit section 1.2, 1.3

Januar 2026
15.01.2026
Installation of vertical waterproofing of the plinth
Arrangement of the floor slab of the 3rd floor of section 1
Completed work on the construction of the pit section 2
Arrangement of concrete preparation of section 1