April 2026
14.04.2026
Construction of the excavation of the 1st phase of construction — 70 percent completed.
Arrangement of a monolithic frame of the 1st stage of the parking lot - work is being carried out on the reinforcement of the floor slab.
Section 1:
Installation of monolithic frame section 1.1 — completed by 90%, work is being carried out on vertical structures on the 8th floor.
Masonry section 1.1 — 60% completed, works are carried out on 5-6 floors.
Installation of vertical waterproofing of section 1.1 — 80% completed.
Arrangement of filling the sinuses of the excavation section 1.1 — completed by 70%.
Section 2:
Arrangement of the pile field section 2.1 - work started on the installation of test piles