September 2026

14.09.2026

Building 1:

Section 1.1

  • Work is underway on installing heating pipes and wall plastering 
  • Installation of the section roof and window structures is nearing completion

Section 1.2-1.3
        • Monolithic frame construction is in progress

Section 1.6-1.7

  • Construction of the monolithic frame has begun

Section 2.1

  • Piling work - 100% complete 